PSC deficiency code 13102: Auxiliary engines and power generation

Category Machinery (SOLAS II-1)
Related certificate Cargo Ship Safety Construction
Main references SOLAS II-1/26 and II-1/41 (main source of electrical power)
Typical action codes 17 (rectify before departure), 30 (detainable) if serious
Commonly detainable? Can be, depending on severity (no statistics claimed)

What PSC officers look for

  • Blackout recovery and load transfer not demonstrated (II-1/41)
  • Generator unable to parallel or share load
  • Fuel system leaks; guards missing
  • Exhaust insulation degraded

Typical root causes

  • Single generator operation becoming normal
  • Deferred auto-start test
  • Poor fuel treatment causing failures
  • Maintenance focused on main engine only

Corrective action (example)

Repair generators and fuel leaks; test blackout recovery; restore guards and insulation; record load test.

Preventive action (example)

Mandatory alternate generator running hours; monthly auto-start test.

Evidence to attach for close-out

  • Load test log
  • Photos of repairs
  • Fuel analysis if applicable
  • PMS closure

Related

  • Codes: 13101, 04103, 02108
  • SIRE 2.0: Chapter 8 (machinery) (chapter reference only)

Generate a close-out report for this finding · Download the CAP template


Official code list: Paris MoU, List of Deficiency Codes (1 July 2026). Action codes: Paris MoU, Inspection outcome. Reviewed by: _pending_ · Review date: _pending_ This page is general guidance, not legal, flag or class advice. Always follow the PSC officer's instructions and your flag and class requirements.